Bolton Clarke Network Infrastructure Upgrade

Client Overview
Bolton Clarke is one of Australia’s largest aged care and community living providers, delivering high-quality care supported by advanced digital systems. To improve connectivity and security across one of their key facilities, they engaged Total Fibre & Data (TFD) to complete a full network infrastructure upgrade, including Wi-Fi, CCTV, racks, and structured cabling.

The Brief: Modernising a Complex Site
Bolton Clarke required a complete audit of their existing CCTV, Wi-Fi, communication racks, and network cabling infrastructure. TFD was engaged to complete pre-deployment Wi-Fi surveys, produce audit reports and recommendations, and then deliver the end-to-end rollout.
The project included supplying and installing new fibre and Cat6A cabling, racks, power circuits, and CCTV equipment, as well as integrating client-supplied switches, Wi-Fi devices, and UPS units. All systems were to be commissioned, documented, and handed over ready for operation.
Delivering the Upgrade
TFD delivered this large-scale upgrade across multiple disciplines, ensuring minimal disruption to daily operations while modernising the site’s entire network backbone.
Wi-Fi Infrastructure
- Completed pre-deployment Wi-Fi reports and surveys
- Installed 123 indoor WAPs (Wireless Access Points) and 15 outdoor WAPs
- Supplied and installed up to 89 hatches for ceiling-mounted WAPs
- Removed 35 existing WAPs
- Completed extensive conduit works through basement areas
- Installed client-supplied switches and UPS units
- Provided as-built documentation and safe work documentation
- Commissioned all Wi-Fi network equipment
Network Data Points
- Installed 1 x dual Cat6A outlet
- Installed 11 x single Cat6A outlets
- Routed conduit throughout basement areas
- Tested and certified all Cat6A cabling
New Comms Rack (C7)
- Supplied and installed 1 x 42RU communication rack (800mm wide x 800mm deep)
- Supplied and installed 1 x 20A circuit with 2 x 10A double power points to the local switchboard
- Supplied and installed earthing to the rack
- Supplied and installed 12-core OM4 MM fibre to Comms Room 1 (Main Comms Room)
- X-rayed and core-holed the floor above and below
- Installed client-supplied switches and UPS
New Comms Rack (C8)
- Supplied and installed 1 x 42RU communication rack (800mm wide x 800mm deep)
- Supplied and installed 1 x 20A circuit with 2 x 10A double power points to the local switchboard
- Supplied and installed earthing to the rack
- Supplied and installed 12-core OM4 MM fibre to Comms Room 1 (Main Comms Room)
- X-rayed and core-holed the floor above and below
- Installed client-supplied switches and UPS
Existing Comms Racks (C4, C5, C6)
- Supplied and installed new 12-core OM4 MM fibre to each rack
- Installed new FOBOTs in each rack
- Supplied and installed 1 x 20A circuit with 2 x 10A double power points to the local switchboard
CCTV Works
- Installed 101 x CCTV cameras
- Installed 2 x ANPR licence plate cameras
- Installed 1 x 128-channel NVR
- Installed 12 x 10TB hard drives (configured for approx. 3 months retention; to be reviewed at 8 and 12 weeks)
- Installed 4 x 16-channel NVRs and monitors for nurse stations
- Removed 6 existing cameras
- Completed conduit works for CCTV infrastructure
- Completed CCTV system design and commissioning
The Result: Faster, More Reliable Network Performance
The result was a fully modernised, high-performance network that now supports Bolton Clarke’s operational and care delivery requirements. Staff can access fast, reliable Wi-Fi throughout the site, while residents benefit from stronger connectivity for their personal devices and online services. The new CCTV system provides complete site coverage and improved security visibility, while the upgraded racks, fibre backbone, and certified Cat6A cabling provide a stable foundation for future digital upgrades.
Bolton Clarke reported significant improvements in network performance and reliability following the upgrade, with staff noting faster Wi-Fi speeds and seamless site-wide coverage.
Services delivered on this project: Wi-Fi design and installation, commercial data cabling and comms rack fit-outs, and CCTV installation.
How TFD Delivers Large-Scale Network Projects
This project demonstrates TFD’s capability to deliver complex, multi-technology infrastructure upgrades, including Wi-Fi design and installation, fibre optic cabling, Cat6A cabling, CCTV systems, rack upgrades, power installations, UPS integration, and commissioning. We also provide full safe work documentation and as-built handover packages for compliance and asset management.
We regularly support IT teams, electrical contractors, and security companies who need a trusted partner for large-scale infrastructure works—delivering specialist services without competing for their clients.
Need to modernise your network infrastructure?
Partner with Total Fibre & Data for certified design, installation, and commissioning services.
Contact us today to discuss your project requirements.
Blog Posts
-
Cat6 vs Cat6A: Which Does a Commercial Office Actually Need?
-
Access Control Specification: A Door-by-Door Checklist
-
Business Security Cameras: How to Plan a Commercial CCTV System That Scales
-
Security System Installation in Brisbane: What a Commercial Site Should Specify
-
Data Cabling Installation for Commercial Sites: From Site Survey to Certification
-
Access Control Systems: Why Backbone Cabling Makes or Breaks Security
Projects
-
Chandler Site: Aerial Fibre Between Three Buildings for Uhaul Australia
-
Griffith University Village — Fibre, Cat6A, and Rack Installation with CommScope Certification for MACO Electrics
-
Minnippi Golf & Range — Fibre Repair, Testing, and Certification for Lynx Electrical
-
Whatalec Education Campus Fibre Splicing and Certification
-
Bolton Clarke Network Infrastructure Upgrade
-
MACO Electrics – Griffith University Village